Westbury PH.2, Lexington Park, MD

Attention: open in a new window. Print

Download PDF of this Project

Lexington Park, MDwestbury phase 2

Owner
The Ryland Group, Inc.
4100 Monument Corner Drive
Fairfax, VA 22030
Dave Ostrander
(703) 502-5200

Project Type
Residential Sitework - 50 +/- acres

Sargent Corporation’s Role
Subcontractor

Engineer
Metro Landfill Services, Inc.
4025 Jermantown Road
Fairfax, VA 22030
Scott Cruise
(703) 615-3145

Start/Finish

August 2005 - May 2006

Description/Significance
This 50 acre residential site development when finished will have 228 single family and town homes. Sargent crews were involved from the design stage to finish pavement.

170,000 CY of Excavation
5,910 feet of drainage pipe
6,700 feet of sanitary sewer
7,700 feet of water main
15,000 feet of curb and gutter
8,900 tons of asphalt
15,000 tons of stone